Hi experts ;

While confirming a pipeline material to a production order , the unit price was incorrect , as a result , in FI and CO i have a posting that is incorrect ;

I wounder if there is a way to rectify the problem without making any change to the production order ;

Thks in advance for your help.

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Jul 16, 2016 at 03:30 AM

    Hi,

    Please try to do price change by MR21 tcode try to post.

    Thanks & Regards

    Sandeep Kumar Praharaj

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.