Hi,gurus,

He have a problem with all postings going to DUMMY PC,even though the material s have in their masterdata the profit centers maintained

the problem is that we cannot assign a default profit center to a cost center as there are a lot of profit centers of the materials that should not be compiled into a single one,and to create a cost center for every profit center is also not a viable solution.

As i am not a FICO expert,I would kindly ask for as detailed as possible guidance to overcome this issue.

Thank you

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

3 Answers

  • Best Answer
    Posted on Jul 17, 2016 at 01:26 PM

    Hello,

    If you want to post this account on cost center, cost center works here as real CO object and the postings from real CO object flow online on profit center assigned in cost center master record. If

    no profit center is assigned in cost center master record then profit center dummy is automatically derivated and posted.

    The profit center is not a real account assignment object thus it is not possible to derive the profit center from OKB9 during FI posting.

    Best Regards,

    Owen

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jul 18, 2016 at 05:36 AM

    Dear Raul,

    You also have the option to define profit center via 3KEH (old release) or FAGL3KEH (release with New GL) to define a default profit center for one G/L account.

    Hope it is helpful.

    Best regards,

    Jason

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jul 19, 2016 at 08:54 AM

    Problem solved-the fact is ,as I mentioned,we cannot assign a profit centre to a cost center because we use different profit centers for materials and the same cost center.

    The problem was triggered by the approval process at the purchase requisition level.as it is done via cost center,and the cost center's profit center field was blank,SAP assigned during MIGO the dummy PC.

    The workaround accepted was that after PR approval,before the PR to PO conversion,the account assignment (K) has to be removed,and then MIGO takes the material PC .

    Thanks for your input.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.