Kindly i need to know three points regarding dip in customer service :

Can i configure dip to get planned labor hours and actual posted spare parts on service order in DP90?

What is the usage of selection criteria for sources why should i use sets two times one for source and other in material determination?

Also what is the standard set names which should be used for all activity types, all material, no activity types and no material ?

Thanks

Mohamed

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Jul 13, 2016 at 06:47 AM

    Mohamed

    In the Sources section of your DIP Profile (ODP1) there is an option for Planned Costs - Totals Records.

    This will get the planned costs from the order. You will then need to use the Selection Criteria to restrict which costs to the labour only. If this fails you will need to develop a solution.

    PeteA

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.