on 07-11-2016 9:59 AM
Hi everyone.
1. I create production order
2. Reservations for materials creates too
3. We run MRP
4. After that purchase requisiton creates
Is it possible to do similar process with Service? So I need to plan Service from production order.
I see that I have to use control key with external operation. But I can not see how to put Service to BOM or in the production order.
Hello
If your requirement is to create the service PR with item Category as "D" with the production order control key, than I think it is not possible with the Std SAP.
Regards
SS
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello
You do not put service on a BOM, you set the respective control key to an order operation. During the order creation, a requisition is automatically created and the components assigned to this operation are sent to the vendor.
BR
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.