Budget Transfer query

Hi PS Experts,

I have a question for budget transfer.

I need to transfer budget from WBS 144.1 to WBS 144.2 -- see below screen shot.




Can I transfer budget using CJ34?


I am asking the question because in help.sap.com site, it is mentioned as below

The sender and the recipient cannot belong to the same subtree.


Regds,

Ashwini




Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • Best Answer
    Posted on Jul 05, 2016 at 03:02 PM

    Hi Ashwini,

    You have a check button (F9) in CJ34 to test it... I do not see any issue if these two elements are end-nodes.

    On your screen however those 2 WBS-elements do not look like the end-nodes, and if the budget is allocated further below it can be a consistency issue. If they are end-nodes from the budget allocation perspective theoretically I do not see an issue (because the total amount from the parent perspective does not change).

    Regards,

    Paulo

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.