SNP prod.Horizon and Extend Prod.Horizon

Dears, is any one can explain the difference between SNP prod.horizon and Extend Prod.Horizon.?

If maintained one of the above , the new planned order can not be created in the horizon ,but  if there is still  new planned order created in the horizon ,what 's the problem ?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • avatar image
    Former Member
    Jul 04, 2016 at 01:59 PM

    Hi Dongmei,

    SNP Prod Horizon- SNP does not create any planned orders, SNP deletes all unfixed SNP planned orders from previous planning runs within this horizon.

    Extended Prod Horizon- This horizon is an extension of the SNP Production Horizon. However, in

    contrast to the SNP production horizon, you can manually create SNP planned orders in this extended horizon in interactive Supply Network Planning.

    Could you please elaborate your question?

    Regards

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jul 02, 2016 at 08:29 PM

    Hi dongmei,

    SNP Production horizon - After planning run (SNP and CTM)planned order generate after this horizon days.

    &

    Extend Production horizon - Time period, during which Supply Network Planning (SNP) does not plan production; that is, does not create any SNP planned orders. SNP moves production to the first day after this horizon. This horizon is an extension of the SNP production horizon. However, in contrast to the SNP production horizon, the user can manually create SNP planned orders in this extended horizon in interactive Supply Network Planning.



    Refer : Difference between SNP horizon, SNP production ... | SCN

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jul 20, 2016 at 08:02 AM

    Dear all

    Thank you very much for your explaination.

    I want to know how to keep the volume within the horizon  can not be deleted or new order created after the night heuristic run.Will you please check the master data setting ,if there are some important points missing:

    I using this setting, and I found that after the night job run , the will be order deleted or new order created.

    waiting for your reply, thanks!