SAP APO-SNP Data Integration

Hi all,

I was wondering what are some methods of implementing data integration between a production system and a training environment? I am looking for something that would allow us to apply periodic updates to our training environment in order to keep the data as current as possible to ensure effective training in regards to APO-SNP.

Thank you

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Jul 06, 2016 at 11:01 AM

    Hi Jacob

    I think you have to keep your training system updated into 2 ways.

    1. Technical changes i.e. the enhancement or changes which move to production system also require to move to you training system this you can achieve via creating/maintaining the correct transport landscape i.e. moving the changes to training system while moving to production system. This will allow you to have both the systems on the same page.

    2. Data updates :- This is most challenging part to have update data on training system. I am not sure @ how frequent and how big data you would require on training system but best option would be system copy. You can copy production system to training system. You can also copy the subset of data from from production system to training system using SAP TDMS software.

    I hope this information will help you.

    Thanks

    Amol

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Jacob,

      I agree with Amol. At first you would require to analyze how much important it is for you to have a training system with the latest data. I mean what is the business justification to have the latest data of production in a training system.

      If the requirement is only to keep the configuration elements updated in the training system then you need to move the transports into the training system as soon as they are moved into the production system. For any thing related to data I suppose you may have to convince lot of people with good business justification for having the bulk of the production data into training as generally it does not make much sense to have the whole backup of production data in a training system as it costs much money.

      Regards

      Sasi

  • author's profile photo Former Member
    Former Member
    Posted on Jul 19, 2016 at 03:22 PM

    Hi Jacob,

    the main question is, how you would like to use your system for training or testing activities.
    Normally an APO System is connected to an ERP System. That means if you like to test the SNP business processes in your 'APO QA' System, you need also an 'ERP QA' system.

    If you answer this with an YES, than you need a system landscape copy (ERP with APO etc.). You can find more detailed information in the SAP note 886103.

    Best regards

    Michael

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.