Graphical Planning Board in MF50

tor_holter
Explorer
0 Kudos

Hello,

We have a profile for CM25 that works OK.

Now the planners want to have this layout linked to MF50.

This is done by setting the user parameter KP2 to the overall profile.

Having done that I open MF50 and the planning board  looks OK.

But what is missing is the elements in the Order Pool.

The process orders and planned orders visible in CM25 are now gone.

The two overall profiles are the same except for the control profile.

Anybody out there who are very clever with the intricacies of the graphical planning board who can say anything about the dependencies here

as to why the capacity requirements do not show?

Thank you very much!

Regards,

Tor

Accepted Solutions (1)

Accepted Solutions (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello Tor

Usually, when I have problems in the graphical planning board in transaction MF50 I use the following notes to check:

148177 - MF50: Graphic --> Explanation of graphics profile

185208 - MF50: Collective note --> Explanations as of 4.0

Missing elements are usually related to the selection profile. Are you sure that you are using the same one?

I also suggest you to always ensure that the SAP GUI Patch is updated. See the document 


BR

Caetano

tor_holter
Explorer
0 Kudos

Seems to be some tricks around the grouping of requirements.


The standard is to have all orders on the same line per combination material  - prod. version. as in the tabular layout.

Seems to be some hard coding here which there is a modification for.

In our graphic is one line per individual orders.

I have to read more closely the notes 112750 and 148179.