Dear Gurus,

My client have 4 plants, and 56 different shipping points, and plant can use any shipping point location to deliver the stock.

I can assign many to many relationship in b/w plant and shipping points.

but while in the determination of shipping points system only propose the 12 shipping points (propose and manually entered).

how can i deal with this scenario, i can not enter any other shipping points not available in the determination assignment ?

looking for the gurus feedback, with thanks.

Regards,

Accepted Solutions (0)

Answers (1)

Answers (1)

ravi_kumar100
Active Contributor
0 Kudos

Hi Imran,

The standard will allow to maintain only 11 Shipping points in system. If the requirement is for more then it can be achieved through enhancement as described in the below Note.

101254 - Enhancement to shipping point determination


Check the same and discuss with your Business and technical team to achieve the same.

Regards,

SRK