As per the below details, i have SO for May and June.
I have selected monthly lot size, but system is creating two planned orders for juy two different planned orders
in this case, i need if there are two different planned order in back dated, then sytem should club that two to one planned order and for the future , it is only monthly basis as below..how to configure it?
Hello
You can allow the start in the pas for planned orders in transaction OPPQ, however, requirements in the same month will be covered by a single planned order.
BR
Caetano
Vijesh,
For the same situation if you change the planning date as 30th June in MD03, does the output change?
Best Regards,
Rajen