on 06-27-2016 1:29 AM
Dear Expert,
Working with a co production process(production order created with KKF1)
I want to know if I need to move the material to Quality inspection upon GR which inspection type i need to activate in the material master
Thanks
Faisal
Hi,
For co- product quality process, assign inspection type 05 (goods receipt other) in the material master of respective co-product, After the GR system will create inspection lot for which you can perform result recording and usage decision.
With Regards,
Prathamesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Muhamed,
My understanding is that you may be trying to book activity costs against cost center using CO - Production order using KKF1. If you are doing any Goods Receipt (Ex; MvT 101), then this part can still could still have QM inspection, with inspection type 04 assigned to Material Master.
You can check with one of the expert feedback in the below thread - https://scn.sap.com/thread/3465619
Thanks to Ajay for this advice!
If you have any further specific doubts, please post a separate query in CO Forum.
Thanks,
Arijit
Hi Muhamed,
There are several threads in SCN on the same subject, it will be good if you can explore those inputs to check what is the situation applicable for your process.
Please check if your finished material was in stock, before you try to post GR form CO-order, as thet might not be allowed. Also, once you run a fresh scenario with a new order, it should be better.
Also please try Note 48815, in case of any inconsistency.
Thanks,
Arijit