on 06-21-2016 10:07 AM
Hi,
When we are creating the unit cost estimate in the Sales quotation, for activity types, can we pull the actual price computed using KSII from the previous period?
If yes how can we do that?
Hi Sanjay
The Costing Variant that you use to calculate the Unit Cost Estimate can be configured in the "Valuation Variant" to look at the Actual Price of Previous Period
Ajay M
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.