Hello all,

I am answering a RFI about EAM mobile solution and one of the requirements is to have data synchronized directly with the SAP ECC without the need of an intermediate data server.

Is it possible to synchronize work manager to PM without SMP? Any plan to have it on this way?

Thank you!

Accepted Solutions (1)

Accepted Solutions (1)

bill_froelich
Product and Topic Expert
Product and Topic Expert
0 Kudos
While Work Manager requires SMP it does not store any data in the SMP server layer. There is no intermediate data server as Work Manager directly synchronizes with ECC. SMP is there to manage the interaction between the client and the back end so that the clients do not require direct access to the ECC backend (makes the security folks happier) and to offload some of the processing but no data is stored there