Hi Everyone,
I want to create a project from Template(it has all WBS, Network, activty) in SAP PS through program
I tried using CJWB_PROJECT_COPY but it is not copying WBS elements under the template.It is only creating the project defintion without any WBS elements
I passed Project definition(Template) only to the importing parameter WBS_TO_BE_COPIED. Attached is the screen shot. Did I missed any flag to copy WBS elements.
Please advice.
Thanks&Regards,
Ram.
Hello,
I can see that your question is already 2 months old.
However if you are still struggling with your requirement please note that function module CJWB_PROJECT_COPY works properly only if called together with function modules CJDW_GET_NEW_NUMBERS and CJDT_GET_NEW_NUMBERS.
If interested please check document
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
9 | |
8 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.