on 06-16-2016 10:23 AM
Hi,
The requirement is to enter customs clearance agent's (third party) service charges and other charges (freight/courier) in the Service PO. What can be done for this (and what is the best practice)? Can the condition types to be configured for this (same as materials PO)? Kindly advise.
Thank you,
Hi,
As it has been earlier communicated in SAP note 381030 that delivery cost or other cost are generally not supported in External Service Management, SAP recommends you to add in additional service line.
let suppose you are getting service in line item 10.
so add custom clearance charges in line item 20.
add freight cost in line item 30.
and so on....
after accepting the services, you can change the vendor in MIRO (Inv. Party in Details Tab) for line item 20 & 30.
Try this in your system.
Regards,
Saad
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You are right that line item 20 & 30 will be printed in your PO.
but if you can write something as Freight charges or Insurance charges in Line item text (basically something on which logic can be created by the ABAPER). you can ask him to create a Z-form for this print out omitting the lines of other cost.
Regards,
Saad
Hi,
Can you share more business background where your service needs customs clearance?
If it is related to material you can go for import procurement where material physically stores in customs department and for which you need to pay to customs vendor but in case of service where you are storing?
For service PO, may be you are requiring consulting by consultant or geologist or specialist for which no storage needs in customs department for which payment requires!
Regards,
Biju K
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Bijay,
Thank you for the reply.
The service PO will be lumpsum (materials + services, excluding customs clearance agent fee). Some materials are included in the service PO which will be imported, therefore the requirement is how to handle customs clearance agent fee for this scenario?
Thank you,
Best Regards,
Hi,
Better handle with material procurement with import process where you have material price fro import vendor and customs price for custom vendor. For vendor, those provides the service- you can create a new condition type( have appropriate condition category) for service vendor and add to the Import pricing procedure of material and add service price in material import PO with new condition type and add those vendor in it.
Regards,
Biju K
Thanks Bijay,
But with material PO, can we maintain validity dates?
As mentioned in No. 2 above, if we are just giving customs clearance charges (means Vendor is sending tools and third party vendor is clearing from customs) then in this case how to handle in service PO?
Thanks for any suggestion.
Hi,
Already processes are suggested- Only you need to re-design business process based on your skill and design a import pricing procedure for material where facilitating payment for agency on service with keeping a separate condition type.
Just spent quality times with system, configure as requires, carry out all transactions and cross check accounting entry at the end.
Regards,
Biju K
Hi,
you can maintain/add service line item as custom clearance in service PO.
Regards,
Abhay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear all,
Thank you for the reply. It means the customs clearance should be same as materials conditions type?
Pls advise.
Thank you
Best Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Rosh,
Thank you for the reply. The requirement is to capture customs duty (to be paid to the vendor or to the third party - both scenarios) and customs clearance cost (for third party i.e., customs clearance agent) in the same PO? or what is the best practice for this scenario?
Thank you,
Best Regards,
1) Create surcharge condition for customs duty paid and custom clearance cost.
2) Add this conditions in your pricing procedure.
3) Create Service PO, mention the respective % condition value.
Note:
1) You cannot define different vendor in any of the surcharge conditions as you define in freight condition while procuring goods.
2) You cannot define accrual and account key for these conditions.
3) There are few functional modules which can read the conditional values in PO pricing and give you the amount how much amount you spent for custom duty over the year or certain period.
Hi
add custome condition type JCBD in your pricing procedure and assign the pricing procedure to service vendor in purchasing data and also need to create a new vendor as custm vendor and add in the procedure like
go to conditon tab in the service po and select jcbd condition type and select the details maginfier and add the newly created customer vendor in the bottom of the screen.
it custome charges will be paid to the that vendor ( same process for freight /courier)
Regards
Sudhakar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Yes you can, please call transaction M/10 and define the condition for custom clearance and add the same in your pricing procedure by call transaction M/12.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.