Hello All,

Greeting for the day,

i am facing an issue, while executing a report in PS module.( related to cost element report with WBS and  Network activity type completely customized as per client requirement )

Error " inconsistency in project structure for NWA ". Please let me know, why do we get this error and how to sort it out.

Thanks

Mahender.

Accepted Solutions (0)

Answers (1)

Answers (1)

MTerence
Active Contributor
0 Kudos

Hi,

Kindly share the screenshot and error message details

Is that a customized report or standard report ?

Regards

Terence

Former Member
0 Kudos

Hello Terence,

Kindly excuse ....

Actually that was an information message, not an error message. After pressing enter, we are getting dump error for all the activity types , which are there in the project.

Thanks

Mahender

kenmelching
Active Contributor
0 Kudos

Always click on the Yellow question mark to get additional information and the message number.

Since you are getting an ABAP dump, what is failing?