Skip to Content
avatar image
Former Member

SPPD and SPRD in SPP Supersession

Hi,

Can the SPPD and SPRD be the same ?

Would also like to know is there any settings maintained to check the SPRD date calculation

Regards

Aravind.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Jun 15, 2016 at 12:14 PM

    Hi Aravind,

    SPPD - Successor Product Planning Date --> The date on which your successor product will be started Planning (demands of all the predecessor products will be passed to Successor product)

    SPRD - Successor Product Receipt Date --> the date on which successor product expected to be received in your warehouse.

    Determination of the Successor Product Planning Date - Product Interchangeability in SPP - SAP Library

    SPRD calculation depends upon the DRP MODE you're using at each location.

    Explore SAP help for detailed info

    Just my Thoughts

    Vinoth

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Check if you've any BADI implemented related to INCMD.

      Test the following

      Create a new supersession chain with predecessor having some stock and try running the Superession date calculation service and then validate the results.

      Note - Check the PSM application logs without fail on /sapapo/pe_log_disp

      sorry for late reply, havent been for here quite while

      Just my thoughts

      Vinoth

  • avatar image
    Former Member
    Jun 24, 2016 at 12:05 PM

    Hi Aravind and Vinoth,

    Successor product planning date(SPPD) plus the supplier delivery time to the entry location of BOD = SPRD(Successor Product Receipt Date).

    As per my understanding  SPPD + Planned Delivary time  =  SPRD.

    you can maintain Planned delivery time in the procurement Relation ship Master data and in the location product master data on the procurment tab page.

    Thanks & Regards

    Mallampalli.T

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Aravind,

      As said earlier

      Check if you've any BADI implemented related to INCMD.

      Test the following

      Create a new supersession chain with predecessor having some stock and try running the Superession date calculation service and then validate the results.

      Note - Check the PSM application logs without fail on /sapapo/pe_log_disp

      Its not necessarily that always SPRD = SPPD + PDT, it depends upon the other dates like SED, SEWD, if all these things are in past then you may get SPRD equals SPPD

      sorry for late reply, havent been for here quite while

      Just my thoughts

      Vinoth