Valuation type field in material component in project builder

Feb 08, 2017 at 11:55 AM

48

avatar image
S R

Hi,

We are using split valuated material for project procurement through project builder, but there is no field for valuation type in the material component in CJ20N.

Can anyone please suggest, where we can maintain the valuation type in the material component in CJ20N?

With Regards,

SR

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Yuri Orlov Mar 15, 2017 at 07:11 PM
-1

Hello,

there is no such filed in mat. comp. You can change val. type in MM docs