CM25 - Operation duration shrinked when dispatching

Former Member
0 Kudos

Hi Gurus,

I am experiencing a difference in operation time duration between production orders before and after dispatching.

Here's the situation:

The production order before dispatching:

Start date: 10.06.2016 - Start time: 20:40:00

Finish date: 13.06.2016 - Finish time: 06:37:23

The production order after dispatching:

Start date: 10.06.2016 - Start time: 20:40:00

Finish date: 13.06.2016 - Finish time: 06:20:00


Could you please help me understand the cause of this behavior?


Thank you in advance for your precious help.


Best regards,


Silvia

Accepted Solutions (0)

Answers (1)

Answers (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

It depends upon the strategy profile used in CM25.

If you have use the Close gap, Treatment of queue time and Reduction level.

and scheduling parameter of production order OPU3 for reduction.

Such discussion should be post in production planning forum

Best Regards,

R.Brahmankar

Former Member
0 Kudos

Thank you Brahmankar,

But no queue time exists for any operation, so -as per my understanding- reduction levels should not apply.

Have you got some insights?

Thank you again and regards,

Silvia

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello.

Can you share the screen shot of production order operations details screen and CM25 strategy profile?

Best Regards,

R.Brahmankar

Former Member
0 Kudos

Dear Brahmankar,

Please find the required screenshots.

Could you please help me?