on 06-08-2016 7:31 AM
Hi Experts,
I want to track project progress on the basis of duration ex if a WBS is having a start date 01.06.2016 and will be 100% completed on 30.06.2016 , what configuration should i do .
Regards
Abhishek Singh
Hi Abhishek ,
Check this link for Time Proportionality method
Time Proportionality - Project Progress - SAP Library
Regards,
Islam El-Shamy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi ,
As suggested by Ken , please read on Progress Analysis - Time Proportionality method.
It is a standard approach.
Shubham
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Use Measurement Method Time Proportionality in Progress Analysis configuration.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.