on 06-02-2016 6:19 AM
Greetings Experts,
In our business scenario it is required to incorporate different Person Responsible for individual wbs elements while releasing depending on the nature of work. Currently single person responsible can be assigned while releasing the wbs.
I understand that Validation rules guide the system here, what changes are to be made?
Please guide as to how this can be done.
Regards
Mazal
Hi Mazal,
To achieve it you would require Substitution not Validation.. You can get your technical team to write a small program to check for the WBS the work type and person responsible to be entered for the type of work
You would need to create a Custom Table to store the linkage of work type to person responsible.
if you need multiple person responsible you can use Partners functions in WBS and substitute these..
Hope it helps..
Regards
Sammar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Mazal,
Do you want to maintain multiple person responsible in a WBS element ?
Try to use the User Fields for additional personal responsible. In case if you need F4 list, then you need to go for an enhancement.
Regards
Terence
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
10 | |
6 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.