We are facing one situation where one Asset is got linked to multiple WBS elements.
Please guide me what could be the reason for this situation please.
With Best Regards
MP Vashishth
HI ,
I had the same issue the reason is that we when we copy the Project or WBS element from the existing system copies that Settlement rule as well., both Settlement rule WBS to AUC and AUC to Fixed asset .
If you still want user to copy from existing project then make sure User delete the Settlement rule in new project and create new rule .
So its always preferable that you create standard template for projects and WBS elements .
You can test this in your test system ...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Mahavir,
Do you mean AuC or FXA ?
Regards
Terence
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Actually we have a business scenario where one WBS to link to only one FXA.
Earlier it was working completing fine but now without making any change (as per my knowledge), this kind of situation has occurred.
We do not have any scenario where multiple WBS elements are required to be linked to one Asset.
Please guide.
Wbr
MPVashishth
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.