Capex Budget Release not allowing in CJ32

125 Views

Hello Experts,

For capex budget control we created one project under that WBS has created . Now the issue is for one WBS we maintained budget in cj30 and going to release in CJ32 system is not allowing to release showing error message budget is exhausted particular wbs.

Under that project another wbs has posted cost without maintain any budget . Now we can not able to reverse the document.

But how will system will accept to release the budget for rest wbs.

Anybody can help to avoid budget in availability check particular wbs with in the project or how can I resolve the issue.

Advance thanks for your help.