Transport Target for Business System XXX not found in System Landscape Directory

Hi,

I try to transport directory objects from QA to PROD but import getting error following image. ECC system export/import success but SCM system gettin error. Both system have same SLD configuration.

B.R.

3.png (12.1 kB)
2.png (125.9 kB)
1.png (141.3 kB)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Best Answer
    avatar image
    Former Member
    May 31, 2016 at 10:04 PM

    Hi,

    Did you restart?

    I agree with Apu Das make sure you have created the business system for both QA and Prod. These are different environments.

    Cheers

    Faith

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi,

      Solved my issue, business systems names which had different names in QA and PROD system, fix name then problem solved.

      Thank you for your all replies.

      B.R.

  • May 31, 2016 at 02:37 PM

    Hi,

    Is BS present in your PROD system SLD for SCM system where are you trying to transport.

    Thanks,

    Apu

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    May 31, 2016 at 01:27 PM

    Hi,

    did you try to reset SLD data cache in Integration Builder?

    Kind regards, Moritz