on 03-06-2006 1:50 PM
Could anybody please let me know how to re-schedule the job:
SAP_REORG_NONE_R3_STAT_DB
The job was initially set up by a user who has left, so i'm trying to re-schedule.
I have re-scheduled the job : -
SAP_COLLECTOR_FOR_NONE_R3_STAT, which manages the above, but it doesn't create the SAP_REORG_NONE_R3_STAT_DB job as I was expecting.
Thanks
Ian
Hi Ian,
You could use SM36->Standard Jobs to define the characteristics of the job (i.e. name, ABAP, default variant, frequency) and then re-schedule it from there. If you ever lose the released version of the job again, you would simply go into SM36->Standard Jobs and re-schedule it again.
SAP_REORG_NONE_R3_STAT_DB has a very simple definition - it executes ABAP RSN3_AGGR_REORG on a daily basis. This would be easy to define in SM36->Standard Jobs and make scheduling it easy.
We use SM36->Standard Jobs to define all our housekeeping jobs and then schedule them from there.
Regards,
Gary
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ian,
If you still unable to re-schedule the job, you can change an existing one that was defined by a user who left. The only thing you need to change is User field in the job step.
Here is a brief sequence of steps:
Open SM37, mark the existing job (in a status released on scheduled) and click on Job=>Change. In the next screen click on Step button and then, once you see step details ofor a job go into change mode and change the user field to a user that is active in the system (and is authorized for running this job/program)
Regards,
Mike
User | Count |
---|---|
96 | |
11 | |
11 | |
10 | |
9 | |
7 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.