what is scheduling and floats?? (production order create)

0 Kudos

while creating the production order its need to fill up the scheduling and floats. wants to know details about the scheduling and floats!! 

Accepted Solutions (0)

Answers (3)

Answers (3)

0 Kudos

thanks

Amit_SAP
Active Contributor
0 Kudos

If your query is solved please close the thread.

Regards,

Amit Sharma

0 Kudos

thanks for your reply. specially i want to know about the forward scheduling and backward scheduling in details! 

Amit_SAP
Active Contributor
0 Kudos

Hello

Go through the below links

schedule margin key | SCN

Scheduling Margin key ( Float before production... | SCN

Hope this will help you..!!