Hello Team,
Please guide me in the below issue from client in EHS-SPCIFICATION
"We inherit data from a template specification to a target specification. When we change values in the template specification with a change state, the values in the target specification are changed as well, without taking care of the valid from date of the change state.
An example:
Template specification has a value YYY in value assignment XXX. This value is inherited to a target specification. The template specification value is changed with a change state with a valid from date of 2016-01-01.
The inherited value in the target specification is changed as well. But when we open the target specification with a valid from date of 07-01-2015, it shows the values that were changed in the template specification with a valid from date of 01-01-2016.
Step1: A newly specification created on 05-25-2016.:

Step2:1 inheritance maintained

Step3:The template specification inherits supplier address data to the specification.

Step4:A new change number is added with Valid from date 05-27-2016 . With this change number, the inheritance template is changed from 001000000648 to 001000000649


When jumping back to the specifications creation date (05-25-2016), the inherited data in the value assignment is wrong as below. It shows the supplier values that were inherited on 05-27-2016. We expect to see the values that were inherited on 05-25-2016.

Thanks in advance,
Karthik