Different Work center with different activity type

former_member599669
Participant
0 Kudos

Hi Team,

We have around 150 Work center in a maintenance plant which has 1 cost center and 1 activity type for labour. Now requirement is to maintain different rates for each activity type i.e Labour for each work center. We do not want to make every work center as a different Cost center.

Please suggest How can we have different rates for each work center.

Thanks,

Sahu

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Sahu,

As per my knowledge,

Cost center/Activity type combination can have unique rate for period/fiscal year.

if you want to have different activity rates for each work center then I think you need to create separate activity type for each work center.

Regards,

Amol