We have around 150 Work center in a maintenance plant which has 1 cost center and 1 activity type for labour. Now requirement is to maintain different rates for each activity type i.e Labour for each work center. We do not want to make every work center as a different Cost center.
Please suggest How can we have different rates for each work center.
Thanks,
Sahu
Hi Sahu,
As per my knowledge,
Cost center/Activity type combination can have unique rate for period/fiscal year.
if you want to have different activity rates for each work center then I think you need to create separate activity type for each work center.
Regards,
Amol
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This message was moderated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
86 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.