Dear Experts,

User dont want to delete PR even work order get TECO, for example work order created and required material PR has been created as well through work order and material has been borrowed from other source and job has been completed and user did TECO what happen PR line item get deleted and due to that PO didnt process.

in this regards user want to continue to procure material through work order PR even work order get TECO as the job has been completed.

Thanks