Reorder point and ATP checking rule.

former_member231238
Participant
0 Kudos

dear friends.

in Reorder Planning,

I know the MRP create PR by compare the quantity of Reorder point and the Stock.

my question is , By which ATP checking rule we determine the quantity of Stock here? and where to customize it?

thanks

Tang

Accepted Solutions (1)

Accepted Solutions (1)

former_member233510
Active Contributor
0 Kudos

1) You've to assign Checking Group for Availability Check in MRP 3 view.

2) You've to assign Checking rule to your Plant using transaction OPPJ.

3) You've to customize, what kind of requirements have to be included for calculating required stock quantity for the combination of Availability check & Checking rule by using transaction OPPJ ---> Determine check.

Message was edited by: Rosh A

former_member231238
Participant
0 Kudos

Thank you , Rosh, it seems reasonable. 