in Reorder Planning,
I know the MRP create PR by compare the quantity of Reorder point and the Stock.
my question is , By which ATP checking rule we determine the quantity of Stock here? and where to customize it?
thanks
Tang
1) You've to assign Checking Group for Availability Check in MRP 3 view.
2) You've to assign Checking rule to your Plant using transaction OPPJ.
3) You've to customize, what kind of requirements have to be included for calculating required stock quantity for the combination of Availability check & Checking rule by using transaction OPPJ ---> Determine check.
Message was edited by: Rosh A