on 05-24-2016 4:08 PM
Dear friends.
when I run T-CODE: MD04, to check the STOCK/REQUIREMENTS LIST for my certain Material, in the menu "environment-->ATP Quantities-->the scope of check", I find the checking rule is 01
what I am confusing is the checking rule, from where can it be determined as "01" here?
can I change the checking rule for it? and where can I make customizing?
Thanks .
Tang.
Call transaction OPPJ ---> Select Plant ---> here you've to assign the desired checking rule for your plant.