Dear Experts
I was running heuristics SAP_CDPBP_02 which is not getting execute successfully it showing Executed without result .What are the major settings I need to check .
In settings of heuristic i have maintain scheduling horizon has 20 days .
I have maintain 3 blocks in that two blocks are empty and one block is full . But it is not Increasing size of overloaded block or it is not shortening the free block
I have maintain my strategy profile as below :
Scheduling mode has find slot
finite capacity Time continuous capacity and Bucket capacity
Finiteness lvl 0000
Planning direction backward + Reverse
Your help will be highly appreciated
Thanks & Regards
Jaisree
Hi Jaisree,
Did you maintain the blocks manually or add them as a reference cycle? SAP_CDPBP_02 works based on cycle definitions. Please, make sure that there is a Cycle Start and a Cycle End in the blocks. Then, it should be possible to execute the heuristic for a block that is inside that cycle - if there is an overload in the selected block, the limits will be adjusted so that all activities can be scheduled.
Other than that, SAP_CDPBP_02 will call SAP_CDPBP_01 as a follow-up heuristic to reschedule the activities in the adjusted blocks.
The strategy settings used by SAP_CDPBP_01 are hardcoded, such that changing Strategy Profile will not affect the behavior. The exact strategy can be seen in SAP_CDPBP_01's documentation in /SAPAPO/CDPSC11.
Regards,
Tiago