Hi Gurus,
There is a requirement from our client,
Ours is Discrete- MTS scenario and we are using the PP03 control key (Milestone confirmation).
In CO11N screen, confirmation of the Labor hours to be booked more than the shift hours.
Eg: If 510 Min is the available time in a shift (8.5 Hr), they want to confirm more than 510 Min.
what are the setting to be done and is their any affect on the costing.
eagerly waiting for the experts suggestions.
Regards
Adi
HI Adi,
Based On Your Requirement You Can Give Overload Percentage In The Master Data Of The Work Center.
Thanks & Regards,
Uppalapati Jayadeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
if you want to confirm the activity more than your cycle time to specific production orders then you can confirm by entering that activity to that production order
but if you maintain the overload in the work center then it would cause the cost impact in the standard cost estimation
Regards,
Venkatesh.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.