on 05-23-2016 7:13 AM
Hello
Your screen shot saying that you are trying to remove the lot size entry.
Please note that this is a mandatory field if you are using MRP type other than ND.
Kindly enter any alternate lot size or use MRP type ND in place of PD
Hope this will help
Regards
SS
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello
One more point, With the MRP type ND, your material will be no more in use for the MRP run.
System will not plan the material in the MRP run. This is for your information please. Hope you are aware.