on 05-20-2016 3:31 PM
Hi,
when I try to dispatch the order into individual capacity multiple production orders, it is overlapping and creating overload to the work center.
Also it is allowing gap between one production order to other production order
we are looking for production order continuously assign to work center without gap and overlap in CM27. How to restrict?
Thanks,
Bharath
Hi
Please Re-read PP Master Data
Regards
U Jayadeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
while dragging the production order into individual capacity, it should not overlap to other production order, it should give error if we are dragging. we like to place production order continuously into line.
Also if there is a production order assigned to line, then if I am dragging next production order after some space then system should assign this production order continues to previous order.
Basically we need to assign production order continuously without gap, overlap to the line. we don't like to overload production line.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello
Make sure that the flag "can be used by several operations" is not checked on the work center.
Also, on the routing, make sure that "no overlapping" is set for the operation.
If you want to continuously dispatch the operations to the work center, on your strategy profile make sure that the option below has been defined for the setting "close gaps":
2 | until end of the planning period |
In addition, the flag Insert operation may be set.
BR
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
93 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.