I have internally manufactured products A and B. Product B is used on the BOM of A.
I need to plan the production order of B and A to be produced simultaneously.
Anybody has any idea to achieve this?
Thank you all.
Best regards,
Nacho
Hi Nacho
You can use special procurement '52 Direct production / collective order' for component B. That way, system will create a production order of component B that will be linked to the production order of product A.
BR
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Nacho,
1) Make Part "B" as Phantom Assembly in material master mm02 - mrp 2 - E 50 and create the order of "A". Order will not be created for B automatically A can be produced and B can be consumed.
2) Or dont use scheduling parameters. Make it empty.
3) Or set ROP or demand creation for part A. B order automatically will be created.
Regards
Maddy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
Do you mean production order for A and B should start simultaneously?
In this case you can use the lead time offset functionality of BOM.
Please refer SAP help link on it,
Entering a Lead-Time Offset - BOMs (PP-BD-BOM) - SAP Library
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
In BOM of product A maintain negative lead time offset for product B. And check the requirement dates of A and B.
Please refer this wiki page,
[TEST CASE]How Lead-time offset and Operation LT offset works - ERP Manufacturing (PP) - SCN Wiki
Best Regards,
R.Brahmankar
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.