Hi All,

I have created a project for which I have created 3 'internal activity' and used group workcentre assign on those activity. so I run workforce planning transaction 'CMP2', I can assign person on 1st activity and define it's actual and plan hour but when I'm going to assign other person on remaining activity and define actual and plan hour, SAP gives me display mode for those activity. For reference, below is the screen shot:

So kindly tell me how to assign plan and actual hours of other remaining activities.

Regards,

Faizan

Accepted Solutions (1)

Accepted Solutions (1)

MTerence
Active Contributor
0 Kudos

Hi Faizan,

Go to the Network and check the dates for this activity, looks like the start and finish date is different than the first activity.

In CMP2, the fields will be editable based on the start and finish date of the activity.

Regards

Terence

Former Member
0 Kudos

Hi Maria,

I have checked with network but still I'm not able to add actual and plan hours for other activities. For reference I'm also attaching Network and Workforce Planning screen shot.

Regard,

Faizan

MTerence
Active Contributor
0 Kudos

Hi Faizan,

You need to check the activities. The screenshot you are showing is the network header.

Regards

Terence

Former Member
0 Kudos

Hi Maria,

As you told me on your previous post to check network date so I because of that I share with you network screen shot.For activities date, please find below screen shot of all three activities.

Regard,

Faizan

MTerence
Active Contributor
0 Kudos

Hi Faizan,

Activity 0010 belong to 5th month and Activity 0020 belong to 6th month.

Can you please scroll towards your right side.

Regards

Terence

Former Member
0 Kudos

Hi Maria,

This is because my activity 0010 start date is 19.05.2016 and that activity is for 10 days so it ends 02.06.2016 and second activity 0020 start date is 03.06.2016 and is for 5 days end at 09.06.2016. So due to this, my activity goes to 06th month.

I hope you understand now.

Regards

Faizan

MTerence
Active Contributor
0 Kudos

Hi Faizan,

As per your initial post, you are trying to post hours for Activity 0020, but you have marked it was greyed out in CMP2.

On checking the screen for 0010, it starts on 19.05.2016, so the fields are not greyed out.

Since your second activity 0020, it starts on 03.06.2016, you need to scroll to the next period and enter the hours.

I hope this is the query you are asking. Else do brief about it.

Regards

Terence

Former Member
0 Kudos

Hi Maria,

Thanks now I understand where I was missing..

Regards,

Faizan

Answers (1)

Answers (1)

Former Member
0 Kudos

Can anyone reply me on my question?