Dear All,

We have a Joint Production Scenario, where in the Non Leading Co Product has Fixed Price (Ex: USD 20). The Cost of the Process is USD 100. So the Price of the Leading Product is 80. In Product Cost Planning (Std Cost Estimate) we have no problems.

However, when we do Cost Object controlling, using a Process Order, entire cost is getting posted to the Leading Co Product (USD 100) even after running Tr Code CO8B

The help documents supports the system behaviour

"If you have fixed-price co-products in an order item, no actual costs are distributed to these fixed-price co-products. The actual costs of the joint production process are distributed to all co-products that are not fixed-price co-products. This follows the concept of fixed-price co-products, according to which fixed-price co-products are always carried at the manually entered price and not debited with additional costs."

We would prefer the Order to settle USD 80 (100-20) to the Leading Co Product, else it would result in a Variance.

Request your Expertise

Best Regards

Surya Varma