how to see and transfer availability time or expiry time of each batch from ECC to APO and view it in APO when batch is transferred?

Former Member
0 Kudos

how to see and transfer availability time or expiry time of each batch from ECC to APO and view it in APO when batch is transferred?

3. Shelf life and maturity time of stocks             

If indicator 'Planning with shelf life' is set in the product master, stocks should bear explicit shelf life data. That is only possible if the material is to be handled in batches in the R/3 System and if every batch is provided with an expiry time (end of shelf life). Optionally you can also maintain the availability time (end of maturity time). For the transfer of this data into the APO System, please refer to the following notes:               339576, 391018, 535422.              

This transfer is only possible if 'CDP' is determined as classification system.

can I get more explanation on this

Regards

Accepted Solutions (0)

Answers (1)

Answers (1)

kenneth_snyder
Active Contributor
0 Kudos

You need more explanation on which topic? 

Do you know how to CIF batches to APO?

Do you know how to set the classification system?

Ken

Former Member
0 Kudos

Hi Ken,

Thanks for your response, actually I don't know how to do that, and these are what im trying to do, Like to sending maturation Time and Shelf Life, and how to create all the classes and characteristics, and before that configuration of CDP. 

Regards

Former Member
0 Kudos

So basically what I want to do is using the Shelf life and Maturation Time in my Optimizer Planning.