Plant wise requirement list in production plant for material with SPK-40

87 Views

Dear Experts,

We have a scenario where we are using special procurement key-40 for our FG material in all plant(9) with production plant as our mother plant,

We are getting virtual STO PR when we run MRP in demanding plant and we can see that same virtual STO PR in MD04 at supplying plant and planned order getting generated at supplying plant,

Now our requirement is to get list of either virtual STO PR list in supplying plant or planned order generated in supplying plant against demand from demanding plant,

We tried some standard report like ME5A for purchase requisition and C041, COOIS, MD16 for planned orders,

The constrain is when we use ME5A we dont get any list in supplying plant, and whith CO41, COOIS, MD16 we get list of planned orders but its difficult to differentiate which demand is from which plant,

Is there any other report which we can use to achieve out task, or if any Z report reference for the same would be really helpful

Thanks,

Pratik