cancel
Showing results for 
Search instead for 
Did you mean: 

Planned Order always pegged to VSF

Former Member
0 Kudos

Hi

When looking at the pegged requirement for a planned order it always shows the order is pegged to a series of VSFs. When the order route is viewed it is showing there are dependent requirements being satisfied with the planned order in question, not just forecasted PIRs. This is causing concern in the procurement dept.

I have tested FM md_pegging_nodialog and find it also only returns VSFs as the pegged items. Is there a report or recommendation you have on how to convince purchasing that the MRP generated procurement proposals are actually meeting real dependent requirements and not a forecast several months into the future?

Accepted Solutions (0)

Answers (0)