Former Member
May 05, 2016 at 07:46 AM

Co -Product costing (Joint Production)Problem

154 Views

When i do the cost run i get the error saying - Product "Cost estimate for material/plant is incorrect".

The error message code is CK168.

Right now my Project is Infra .


Here Crusher Production Plant is there with Joint production concept .

1. In Material master the views like General Plant Data/ Storage 1, General Plant Data/Storage 2,Plant Stock, Storage Location Stock views are maintained.



2. In all material Co-Product indicator is set


3. In Main product Cost apportionment structure is maintained in MRP 2 view in which all co-product including header material along with equivalence no are maintained


4. In BOM all co product are maintained with negative sign except Boulder. Also at item level Co-product indicator is Ticked.


Please guide me how to do costing