Hi ,

This is regarding the issue For preventive maintenance work order with Bill of Materials and the Inspection sheet attached in the general task list.

Preventive maintenance work order has weekly plan . Once plan schedule then the work orders created into the future referring to Bill of Materials and the Inspection sheet.

when user start to schedule the work , then any changes which have been made in between to the Inspection sheets or the Bill of Materials are not updated in work order. The work order refers old Inspection sheets or the Bill of Materials which is created at initial stage.

User needed that any changes at any stages in Inspection sheets or the Bill of Materials should be updated automatically in the work order.

Please suggest any way to resolve this issue ..