Dear All

Before Running MRP I have deleted all Planned Orders,

and checked in PLAF table .

Still on running MRP schedules are getting generated for deleted planned orders .

Regards & Thanks

Sushma

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Dear Sushma,

From what I understand of MRP, planned orders are created based on requirements and stock levels. So, if you don't want some planned orders to be created, what you should do is delete the requirements (or increase stock level), so that MRP will not detect any need of creating new planned orders.

Hope this helps you.

Regards,

Alex

Former Member
0 Kudos

Dear Alex

Thanks for the suggestions.

Regards

Sushma