SAP Network Activity Elements scheduling with different work ceters

In ETO scenario, our requirement is to add Activity Elements to the parent Internal activity for breaking down the Internal activity into sub-tasks and do the scheduling at Activity Element level in a sequence.

However ,I am aware that scheduling is not possible at Activity Elements and Activity Elements will inherit Parent Activity scheduled dates.

Is there a way to initiate a sequential scheduling at the Activity Element level?

For Example,

Internal Activity-Power Plant onsite Engineers (Start Date: Feb 1-End Date: March 25)

Activity Element1:Initiation(Feb 1-Feb10)

Activity Element2: Drawings(Feb11-March10)

Activity Element3: Kick Offs(Feb 11-March25)

Can we use an offset to the start or finish of the activity to specify the start/finish of the activity element?