Hi All,

I am facing couple of issues with the planning board.

Issue1: I have created maintenance order and  I have maintained the work, no of people and duration in the operations. Also I have maintained the formulas in the work center. Still I am not getting the requirement assignment tab in the internal tab for that operation. Is that any config setting or work center setting missing?

Issue2 : I believe since the assignment tab is not there, when I do split of the operation and assign the personnel number for dispatch, the information such as personnel number  is not flowing to the order. when I do drag and drop of the operation against the personnel number with out split, the actual personnel number is not getting copied back to the operation from the planning board. is there any exist to capture the personnel number and update the order operation?

Awaiting for response

many thanks in advance

MH

Accepted Solutions (1)

Accepted Solutions (1)

former_member374929
Active Participant
0 Kudos

Hi Manoj,

Have you maintained other formula under Capacities Tab in your Work Center. If not please assign SAP008 there and then check.

Regards,

Asheesh Aswal

Answers (1)

Answers (1)

Ravish
Active Participant
0 Kudos

Hi

Can you check the if work center capacity category is 002? Also check if the control key has Det Capcity Reqmnts check box is checked.

Yes, only if the rqmnts assignment tab is available the backward integration from planning board will happen.