Hi Team
Please refer my attachment. I have requirement on 5th of May for 10 pcs. I have Make to stock production order available on 9th May for 10 pcs. After MRP Run , I am not getting any exception message for this production order. I expect the exception message(Schedule in - Order too late) for this order to pull the order to 5th May. What could be the problem? Can you give some idea?
Thanks
Vijay
Hello,
Check the rescheduling customization setting in OMDW
Rescheduling horizon: It is the number of day for which the system checks whether the fixed replenishment elements should be rescheduled. You can define which specific elements will be included on the rescheduling check. If the flag is unchecked, MRP will not consider the element during the rescheduling check
Please refer this wiki page
http://wiki.sdn.sap.com/wiki/display/ERPMan/What+is+rescheduling+and+how+does+it+work
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.