consumption of packaging material in delivery

Hello

Requirement is to consume the packaging material in the delivery.

We had created new mat type copying VERP.Checked the chk box QTY Update in the config.Now when HU is created the requirement is inventory has to get updated for the packaging material along with Material that is packed.

Thanks in asdvance

Regards

Shekar

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Apr 26, 2016 at 03:10 PM

    have you already posted goods issue for the delivery?

    Just defining quantity update for a material type is by far not enough.

    in the schedule line category you define which movement type will be used for a goods issue

    this category  need to be assigned to a item category,

    the item category has to allow schedule line categories and

    the item category need to be assigned to an item category group,

    the item category group needs to be maintained in the material master.