Hi all,
On ByD, we can execute Supply Planning Runs and Release Purchase Proposal Runs.
And we can create PO Acknowledgement.
To improve the productivity, it is important to follow up the shortage effectively.
Could you tell me your case how-to-follow up the shortage?
For instance 200 materials are ordered to each suppliers. And the 10% materials(20 materials) have shortage or denial. Each materials have more than 3 suppliers.
I think it would be useful if we can execute xxx Runs considering the acknowledgement in sourcing rank. However, it seems not to be able to do such operation at present.
How to improve the productivity - reduce the number of click?
Best regards,
Naoki
Dear Naoki Matsuo,
Yes you are correct there is xxx Runs considering the acknowledgement in sourcing rank. Actually you release PO and then you would get acknowledgement.
May i suggest , since there are more than 3 suppliers for one product, i can recommend you that use Quota arrangement to split 200 into 3 suppliers.
Lets assume a simple scenario.
Supplier A deliver product ABC usually 80% of the ordered
Supplier B deliver product ABC usually 70% of the ordered
Supplier C deliver product ABC usually 60% of the ordered
now you know the capability of the supplier so build a quota arrangement in 3:2:1 for supplier A, B and C respectively.
so now when a 200 comes up, it will be split into 3 suppliers as per your requirement and also the same can be fulfilled.
OR you can think of an Add-on option which should actually get the acknowledgement/confirmation from supplier before order.
Mark this as answered or helpfull, if this helped with your query.
Regards
Leo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Leo,
Thanks for your reply!
Quota Arrangement would be useful strategy to avoid shortage in advance.
Excuse me, one point I'm not clear.
Do you mean that second rank supplier would be assigned automatically if I redo xxx Run after entering shortage with PO acknowledgement?
Best regards,
Naoki
Dear Ms. Naoki,
Quota arrangement has nothing to do with acknowledgement here. Here you would create quota arrangement based on capability of the supplier which means
in simple terms instead of taking 200 ea from one supplier you will source 200 ea from 2 or 3 supplier that way the option of fall-back or shortage doesnt arrive.
But this is just a suggestion and your requirement which is mentioned in first question "I think it would be useful if we can execute xxx Runs considering the acknowledgement in sourcing rank. However, it seems not to be able to do such operation at present." is not supported
Check the help document "Source Determination" for example of quota arrangement.
Mark this as answered or helpfull, if this helped with your query.
Regards
Leo
User | Count |
---|---|
91 | |
11 | |
10 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.