Block Marketing Document & payment if exceed the budget

Dear Experts ,

Is there any system feature to block creation of Marketing Documents PR, PO , GRPO, Invoices , etc.. and payments if it exceed the related budget of the Cost center and distribution rule ?

What am thinking is handle it through SP , any ideas ?

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

2 Answers

  • Best Answer
    Posted on Apr 25, 2016 at 09:05 AM

    Hi Mohammed,

    I think SP is the best way...

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Apr 24, 2016 at 04:43 PM

    Hi Mohammad,

    Yes there is a System feature also, Go to Administration --> System initialization --> General Settings

    Under General Setting click on Cost Accounting Tab, In Cost Accounting Tab click on Browse button near Distribution rule where you can set Block Posting.

    By doing this it will block the document when it exceeds the budget set.

    Another way is to block through SP.

    Hope this clears to you. Let me know if you need further info.

    Thanks,

    Harshal

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.